Sikh Community Allows to Pull Down Gurudwara to Construct a National Highway in Srinagar

The existing building of Gurdwara Damdama Sahib will demolished and shifted to another place in the city

 

SRINAGAR| A welcoming motion by Sikh community officials in Kashmir giving green flag to pull down a 72-year-old Gurudwara for the construction of a national highway connecting Srinagar with Baramulla on Thursday.

The reports states the existing building of Gurdwara Damdama Sahib established in 1947 is located along the Srinagar-Baramulla road. It will now be demolished and shifted to another place in the city following an understanding between the Gurdwara management and the Development Commissioner, Srinagar.

Gurdwara Damdama Sahib is known for its service towards migrant families who arrived from Pakistan. The Gurudwara organizes langars and also undertakes many social service initiatives. It had also sheltered flood and earthquake victims.

“Finally, today in the presence of the deputy commissioner and the Gurudwara management, the demolition of Gurudwara Damdama Saheb was started. The Gurudwara will function from a makeshift space until a new one is constructed at the agreed location. The state public works department (PWD) has been entrusted with the construction of the gurudwara as per the design provided by the Sikh community,” the official said, reported in News 18.

The Government of India started construction of the national highway from Srinagar to Baramulla in 2006. Later, the project was funded under the Prime Minister’s Development Plan, an official added.

The Srinagar-Baramulla stretch is executed by the Border Roads Organisation while the Anantnag-Srinagar part is done by the NHAI.

The road was completed in 2013. However, there were few litigations in the High Court concerning the road project. The landowner whose land was suggested for the relocation of Gurdwara had objected to the proposal and obtained a stay in 2014.

Also Read: Jammu-Srinagar NH reopened after two days

The Gurudwara was one of four bottlenecks in the road project, most parts of which were completed in 2013. Apart from the Gurudwara, the three other bottlenecks were a power line, a petrol pump, and water supply lines.

The official said the work on the demolition of the petrol pump and shifting of power lines and water supply lines has also started. The work is likely to be completed in the next 10 days, he said.